Sahuarita-Nogales Transmission Line Project

The Department of Energy (DOE) announces the availability of
the "Tucson Electric Power Company (TEP) Sahuarita-Nogales
Transmission Line Draft Environmental Impact Statement" (DOE/EIS-0336)
for public review and comment.
The Draft EIS was prepared pursuant to the National
Environmental Policy Act of 1969 (NEPA), as amended, 42 U.S.C. 4321 et
seq., the Council on Environmental Quality NEPA regulations, 40 CFR
parts 1500-1508, and the DOE NEPA regulations, 10 CFR part 1021. The
Draft EIS evaluates the environmental impacts of the proposed action of
granting a Presidential permit for the proposed project and reasonable
alternatives, including the "No Action" alternative of denying the
permit. The U.S. Forest Service (USFS), the Bureau of Land Management
(BLM), and the U.S. Section of the International Boundary and Water
Commission (USIBWC) are cooperating agencies in the preparation of this
Draft EIS.
Back
to Top
Home | Draft EIS | Project Documents
| Commenting to DOE | News
Scoping Meeting Transcripts | Governmental
Correspondence Fact Sheet | Maps
| Federal Register Notices | Related
NEPA Links


|